You Are Here: News > Bridge Re-opens After Months of Work / December 24, 2011 12:00 pm

The replacement of the Humber St bridge in Oamaru has finally been completed – behind the original schedule and over budget.

The bridge was closed in mid-July and work was scheduled to take about 14 weeks, but in early September it was found that rock under the northern abutment was too solid for piles to be driven to the depth specified by seismic requirements.

Read full article

Categorised in: